Magnavale Easton Phase II Update

Latest News & Articles With the finish line in sight, we are excited to announce that construction of the new Magnavale cold store at Easton is entering its final stages, with exclusive access to the new facility now being allowed for our strategic partners. The main building and plant rooms are now fully complete, and […]

Magnavale Easton Phase II Update: Envelope is Complete

Latest News & Articles With the finish line rapidly approaching, in Q3 2024, we are delighted to announce that the external structure of our new 101,000 pallet temperature-controlled facility is now complete! Along with the completion of the cladding, the Magnavale areas of the Sadel Food Hub are taking shape with the yard works, including […]

Planning Permission Granted for Sadel Group’s First Food Hub

Sadel Group's Food Hub

Latest News & Articles Planning permission has been granted for us at Sadel Group to develop a new food processing facility at our site in Easton, Lincolnshire. Alongside the new 200,000 sq ft food processing development, our fully owned Cold Storage platform Magnavale is currently constructing a £130m, fully automated, 101,000 pallet cold storage facility, […]

Magnavale Chesterfield Expansion Continues to Take Shape

Latest News & Articles Magnavale are extremely proud to announce they have secured both planning and funding to construct a single, fully automated cold store with a capacity of 101,000 pallet spaces. Being built as an entirely new store, rather than joined onto an existing facility the store will be the largest ever built in […]

Magnavale Easton Nears Completion with Installation of Monorail

Introducing the New Magnavale Easton Monorails

Latest News & Articles As we prepare for the launch of our new 101,000-pallet cold store, Magnavale Easton, we are excited to share the installation of high-speed monorails. Installation began in July 2023, with the monorail system being one of the most technically challenging aspects of the overall infrastructure. The construction took 4 months, wrapping […]

£130 Million Magnavale Easton Development Over 75% Complete

£130 Million Magnavale Easton Development Over 75% Complete

Latest News & Articles Magnavale, a UK-based provider of temperature-controlled storage, has announced that its £130m fully automated facility located in Easton, Grantham remains on schedule for completion in late 2024. The project, which commenced in 2022, will include 101,000 frozen pallet positions contained in a 45-metre high facility along with several floors in the […]

£130 Million Investment into Europe’s Most Efficient Cold Store Facility

£130 Million Investment into Europe’s Most Efficient Cold Store Facility

Latest News & Articles Sadel has announced that they have made a £130 million investment into their new cold store development in Easton Lincolnshire, under the Magnavale brand. The 101,000-pallet cold store will be the highest cold store built in the UK, at 47.5 metres high, allowing greater capacity and efficiency in a smaller footprint. […]

Magnavale Announces Expansion of Chesterfield Facility – Adding 23,000 Pallet Locations

Latest News & Articles Magnavale, one of the UK’s leading providers of temperature-controlled storage, is constructing a significant expansion to its Chesterfield cold storage facility, adding a huge 23,000 pallet locations to an existing ~40,000, currently at the site. Having now broken ground, the provider of temperature-controlled storage, is making steady progress with the groundwork […]

Magnavale Easton Expands Service Portfolio with Blast Freezing

Magnavale Easton Expands Service Portfolio with Blast Freezing

Latest News & Articles Magnavale announce Magnavale Easton Ltd now offers Blast Freezing in addition to Frozen Storage and value added services! Blast Freezing, one of the most efficient methods of freezing large quantities of food product, is relied on by food manufacturers worldwide. Magnavale now offers blast freezing solutions at all four Magnavale facilities […]

Construction Underway at Magnavale Easton

Construction Underway at Magnavale Easton

Latest News & Articles During 2021, Magnavale announced that they secured the planning and funding to construct a fully automated 101,000 pallet cold storage facility which will run entirely on renewable energy. The providers of Temperature-Controlled Storage are extremely pleased to announce Magnavale Easton Phase 2 has now broken ground and is progressing rapidly, with […]